2010 Construction Projects List
 
Road Construction
Traffic
Sidewalk
Flood Preparedness


Village Projects

1. 2010 STREET RESURFACING PROGRAM
Description: 20 streets / 5.0 miles of intermittent curb repair and asphalt resurfacing at various locations throughout the Village. Click here for a list of streets and status of the construction work.
Cost: $2,580,000
Contractor: Arrow Road Construction Company
Schedule: Start work / April 2010 Completion / September 2010

2. LINNEMAN ROAD ERP STREET RESURFACING (Golf Road to Dempster Street)
Description: Intermittent curb repair and asphalt resurfacing funded by the State of Illinois Emergency Repair Program (ERP).
Cost: $430,000
Contractor: Arrow Road Construction
Schedule: Start work / April 2010 Completion / October 2010

3. 2010 SIDEWALK IMPROVEMENT PROGRAM (Various locations throughout the Village)
Description: Sidewalk Replacement Program by request of property owners.
Cost: $40,000
Contractor: Copenhaver Construction
Schedule: Start work / June 2010 Completion / September 2010

4. 2010 CDBG SIDEWALK IMPROVEMENT
Description: Complete missing sections of sidewalk on the north and south sides of Algonquin Road, from Busse Road east to the Village limits; on the south side of Algonquin Road, from Nordic Road to Elmhurst Road; and on the north side of Oakton Street from Badger Road west to the Village limits.
Cost: $120,000
Contractor: Strada Construction
Schedule: Start work / June 2010 Completion / September 2010

5. KENSINGTON BUSINESS CENTER POND 5A IMPROVEMENTS (Feehanville Drive west of Kingston Court)
Description: Dredging and bank stabilization.
Cost: $128,000
Contractor: Undetermined / Bid Opening in August
Schedule: Start work / September 2010 Completion / September 2008

6. PROSPECT AVENUE EECBG STREET LIGHT IMPROVEMENT PROJECT (Maple Street to Pine Street)
Description: Replace existing street lights and pedestrian lights or Install new lights that are LED energy efficient lights utilizing Energy Efficiency and Conservation Block Grant Program (EECBG).
Cost: $150,000
Consultant: Undetermined
Schedule: Start work / Summer 2010 Completion / Fall 2010

7. KENSINGTON BUSINESS CENTER EECBG STREET LIGHT IMPROVEMENT PROJECT (Feehanville Drive and Business Center Drive)
Description: Replace existing street lights with new LED energy efficient lights that are utilizing Energy Efficiency and Conservation Block Grant Program (EECBG).
Cost: $82,000
Consultant: Undetermined
Schedule: Start work / Summer 2010 Completion / Fall 2010

8. LED TRAFFIC SIGNAL RETROFIT PROJECT (Various Locations)
Description: Replace existing traffic signal lights with new LED energy efficient lights utilizing Grant from IDOT.
Cost: $230,000
Consultant: Undetermined
Schedule: Start work / Fall 2010 Completion / Winter 2010

9. COMBINED SEWER REPAIR PROGRAM (Various locations throughout the Village)
Description: Sewer point repairs and cured in place lining of existing combined sewers.
Cost: $1,200,000
Contractor: Undetermined
Schedule: Start work / June 2010 Completion / October 2010

 


 

ILLINOIS DEPARTMENT OF TRANSPORTATION PROJECTS

10. MILWAUKEE AVENUE (ROUTE 21) RECONSTRUCTION
Description: Complete reconstruction of Milwaukee Avenue including realignment of the River Road intersection. The only portion of this project within Mount Prospect is the modifications to the River Road and Seminole Lane traffic signals.
Cost: $13,325,000
Contractor: Plote, Inc.
Schedule: Start work / Spring 2008 Completion / Summer 2010
 

 

COOK COUNTY HIGHWAY DEPARTMENT PROJECTS

11. MOUNT PROSPECT ROAD PATCHING IMPROVEMENTS (Northwest Highway to Dempster Street)
Description: Patching and grinding of existing concrete pavement.
Cost: $1,536,000
Contractor: Greco Contractors
Schedule: Start work / April 2010 Completion / Fall 2010

12. DEMPSTER STREET RECONSTRUCTION (Elmhurst Road to Algonquin Road)
Description: Complete removal and replacement of pavement including curb and gutter.
Cost: $5,400,000
Contractor: Greco Contractors
Schedule: Start work / May 2010 Completion / Winter 2010
 

 

ARMY CORPS OF ENGINEERS PROJECTS

13. LEVEE 37 / US ARMY CORPS OF ENGINEERS, PHASE II (Along River Road and Milwaukee Avenue from Euclid to Palatine)
Description: Construct levee wall and pump stations along the west side of River Road and Milwaukee Avenue to protect subdivisions west of Des Plaines River.
Cost: $23,000,000
Contractor: Vistas Construction
Schedule: Start work / April 2009 Completion / 2011